How to adjust Buyout costs: Difference between revisions

From Tygron Preview Support Wiki
Jump to navigation Jump to search
No edit summary
No edit summary
 
(One intermediate revision by one other user not shown)
Line 1: Line 1:
The [[Buyout_cost_(Function_Value)|Buy Out]] fee are the costs involved with the relocation of residents, when demolishing a [[Construction|building]] that is not [[Construction#Vacancy|vacant]]. These costs can have a high impact on planned projects. Adjusting these costs can be done in the Function Value panel for each structure in the project area.
The [[Buyout_cost_(Function_Value)|Buy Out]] fee are the costs involved with the relocation of residents, when demolishing a [[Building|building]] that is not [[Building#Vacancy|vacant]]. These costs can have a high impact on planned projects. Adjusting these costs can be done in the Function Value panel for each structure in the project area.
[[File:Buyout_Cost.JPG|350px|thumb|Adjusting Demolition Costs during a session]]
[[File:Buyout_Cost.JPG|350px|thumb|Adjusting Demolition Costs during a session]]
{{editor location|function values}}
{{editor location|function values}}
Line 9: Line 9:
|}}
|}}


==See also==
{{article end
|seealso=
*[[Cost]]
*[[Cost]]
}}
[[Category:How-to's]]

Latest revision as of 13:20, 30 January 2024

The Buy Out fee are the costs involved with the relocation of residents, when demolishing a building that is not vacant. These costs can have a high impact on planned projects. Adjusting these costs can be done in the Function Value panel for each structure in the project area.

Adjusting Demolition Costs during a session
Editor → Current Situation (Ribbon tab) → Buildings (Ribbon bar) → Edit Function Values (Dropdown)
How to How to adjust Demolition Costs:
  1. Open Edit Function values
  2. Use the bottom scroll bar to navigate to the right
  3. By double-clicking on the value the Buyout Cost can be adjusted

See also