During business hours ({{business hours}}), there is a maximum calculation time of 1 hour. If a calculation takes longer than that, it will time out after 1 hour. Outside of business hours, calculations will not time out. If necessary, it is possible to schedule the recalculation of overlays for after-business hours. | During business hours ({{business hours}}), there is a maximum calculation time of 1 hour. If a calculation takes longer than that, it will time out after 1 hour. Outside of business hours, calculations will not time out. If necessary, it is possible to schedule the recalculation of overlays for after-business hours. | ||
{{Editor steps | {{Editor steps | ||
|title=postpone grid overlay recalculation | |title=postpone grid overlay recalculation | ||
Line 12: | Line 11: | ||
|Click on ''OK'' to Schedule the update. | |Click on ''OK'' to Schedule the update. | ||
|}} | |}} | ||
<br style="clear:left"> | |||
[[File:Schedule_update_panel.jpg|left|frame|An update can be schedule by clicking on the ''Schedule Update'' link.]] | |||
[[File:Grid_overlay_schedule_update_changed.jpg|left|frame|The ''Schedule Update'' link has changed to the date at which it will be updated.]] | |||
[[File:Grid_overlay_schedule_update_changed.jpg| | |||
{{article end | {{article end | ||
|seealso=*[[Grid Overlay]] | |seealso=*[[Grid Overlay]] | ||
*[[Calculation panel]] | |||
}} | }} | ||
[[Category:How-to's]] | [[Category:How-to's]] |
Latest revision as of 09:04, 31 January 2024
During business hours (9-17, GMT+1, during weekdays), there is a maximum calculation time of 1 hour. If a calculation takes longer than that, it will time out after 1 hour. Outside of business hours, calculations will not time out. If necessary, it is possible to schedule the recalculation of overlays for after-business hours.
How to postpone grid overlay recalculation:
- Select any grid overlay in the editor.
- On the right panel, select "Schedule Update".
- A Schedule Update panel will open
- Select in what way you want to receive a message once the calculation is complete.
- Select at what time you want to the calculations to commence.
- Click on OK to Schedule the update.